Changing your mind during the build: the effect on cost and programme

Wanting changes once the walls go up is natural; what a change costs depends on the stage and on the work it undoes. Knock-on effects, substitute materials and a written change procedure, explained.

Changing your mind during the build: the effect on cost and programme

The moment the frame is up and you walk through the rooms at their real size for the first time, ideas start to come: a wider window here, no wall between kitchen and living room, a second basin in the bathroom. That is entirely natural; scale and daylight that you can't feel on paper read very differently on site. The problem is never the change itself, but asking for it without knowing what it will cost and how it will move the programme. Below, from our experience on site, we look at what a change brings at each stage and how to manage it, including when you are making decisions from abroad.

1. Where changes come from

Changes requested by owners usually have three sources:

  • Seeing it on site: a proportion, a view or a patch of light that wasn't obvious on the drawings.
  • A new need: a change in the family, a decision to let the house, an elderly parent moving in.
  • A product that can't be had: a discontinued tile range, a delivery time that suddenly stretches.

Then there are changes the owner never asked for but the site forces: unexpected ground conditions in the excavation, or damage found when an old building is opened up. It is worth keeping the two apart, because who pays depends on how the contract defines these situations. A contractor putting right its own mistake is not a change at all.

2. The same decision costs differently at each stage

Imagine you want to move the wall between the kitchen and the living room by a metre:

  • At drawing stage: the plan and the 3D views are updated; no materials are wasted.
  • After the permit drawings are approved: if the wall is not structural, often only the construction drawings change; if it affects the structure, the façade or the floor area, a formal amendment to the approved project may be needed.
  • During the frame: easy if the wall hasn't been built; if it has, it means demolition, rubble and rebuilding.
  • After first-fix services: sockets, switches, an air-conditioning pipe and perhaps a drain run in that wall move too.
  • During finishes: plaster, screed, tiles, paint, a suspended ceiling and joinery made to fit that wall are all redone.

A few hours' correction on a drawing becomes, at finishing stage, a job that calls several trades back. How deciding on screen pulls changes back to the cheap stage is covered in our article on 3D visualisation.

What a change really costs is usually set not by the change itself, but by the work it undoes.

3. Seeing the knock-on effects in advance

When one item changes, writing down everything that depends on it avoids surprises:

  • A bigger window: the lintel and possibly a structural check, the façade elevation, the window order, the curtain box and blind size, the room's solar gain and air-conditioning capacity, the furniture layout.
  • A bath instead of a shower: drain position and fall, the area of waterproofing, the load of a full bath on the floor slab, tile quantities, the type of mixer.
  • Moving the hob onto an island: a power or gas supply through the floor, a duct route in the ceiling for the extractor, sockets and lighting on the island.

On a project where the architect who drew it also runs the site, this list comes from the person who knows the logic of the drawings.

Gusto Ephesus, Izmir: the shop after completion
Gusto Ephesus, Izmir: a 40 m² olive oil shop we first designed in 3D and then built, showing the counter, shelving and lighting

4. When a product can't be had: choosing an equivalent

When a chosen product is discontinued, or its delivery time would push the programme back, you move to an equivalent. If "equivalent" isn't defined, an argument is very likely to follow. So the properties that must stay the same, such as size, surface, quality grade and colour range, should be written down, and the proposed product approved on a sample. A substitution caused by the contractor's own purchasing is not the same as the owner choosing something new; if there is a price difference, the contract should say who carries it.

5. A written change procedure

In British contracts these are often called variations. A procedure that works has five steps:

  1. Request: what changes, where and why, in writing, with a simple sketch if needed.
  2. Impact assessment: the cost difference (including items that come out, not only those added), the effect on the programme, other items affected and whether a permit is needed.
  3. Approval: signed approval once the impact has been seen in writing. Nothing is agreed verbally on a quick site visit.
  4. Execution: only after approval.
  5. Record: the change is added to the construction drawings and to the updated drawings handed over at the end.

If you are abroad, the same steps work by email: a written request and sketch from you, drawings or a 3D view and a written impact note back, and your written approval. We explain why this procedure belongs in the contract in our article on turnkey construction contracts.

6. Changes that affect the permit

Changes to the façade, to window sizes on the façade, to the structure, to the floor area or to the building's levels may amount to a departure from the approved project. A project amendment and permit process may then be needed; skip it, and problems can surface when you apply for the iskan (occupancy permit). Confirm with the architect of record and the municipality which changes need permission; the building inspection company is also informed during this process.

7. The way to fewer changes: decisions on time

Many changes come from decisions made late. Decision deadlines written into the work programme prevent that:

  • Light and socket positions before first-fix electrics.
  • Concealed cisterns and built-in mixers before first-fix plumbing.
  • Window sizes and frame colour before the order is placed.
  • Kitchen and wardrobe layout before services go in; final dimensions after plastering.

By contrast, loose furniture, the light fittings themselves (not their positions), curtains and parts of the garden can change later at little cost, so leaving them open takes pressure off. When each stage closes is covered in our article on checks at each construction stage.

Fethiye residential project: kitchen axonometric and materials palette
Fethiye residential project: axonometric view of the L-shaped kitchen, cabinet elevations and a materials palette showing floor, worktop, wall tile, cabinet colour and handles

You can read how we work, with the architect who draws the project also running the site, on our construction in Fethiye page.

Frequently asked questions

Can I request changes while I'm abroad?

Yes. Send the request in writing with a sketch; you receive the drawings or a 3D view and a written note of the cost and programme impact, and the change goes ahead once you approve in writing.

Will a change affect my occupancy permit (iskan)?

It can, if it changes the façade, structure, floor area or levels shown in the approved project. Check with the architect of record and the municipality before the work is done, not after.

If a product is discontinued, who pays the difference?

That depends on the cause and on the contract. A substitution forced by the contractor's purchasing is treated differently from a new choice by the owner, so the contract should spell out how price differences are handled.

If you want decisions on your build or renovation placed at the right moment, get in touch and we will set up the project and work programme together.

  • inşaatta değişiklik
  • değişiklik talebi
  • iş programı
  • inşaat maliyeti
  • Fethiye inşaat
Architecture & Construction

Related service

Architecture & Construction

Let's talk about your project

Your plot, your home or your renovation plan — we map out the way forward in the first meeting.